Accepted programme
Within the NEC Engineering and Construction Contract (ECC), the ‘accepted programme’, is identified within the Contract Data.
The contractor prepares a programme for the works, which is then submitted to the project manager for their approval. If it is approved, this becomes the 'accepted programme'. The programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resource they intend to use. Ref. NEC Dictionary.
The contract may also require that a revised programme is prepared regularly, setting out the sequence of activities, progress, and the effect of compensation events. This must then be submitted to the project manager, and if accepted, this becomes the accepted programme, sometimes referred to as the updated programme. The final updated programme will show the as-built programme.
Within the ECC, the ‘activity schedule’ allocates a price to each activity undertaken during the works. This simplifies the administration of the interim payment process. The accepted programme shows how the activities on the activity schedule are programmed. The accepted programme and the activity schedule need not show exactly the same activities, but there should be correlation between them, and they should be kept up to date.
Without an accepted programme the contract cannot be administered properly. Under such circumstances, 25% of payments can be withheld, and it is not possible to assess compensation events.
Accepting the programme does not discharge the contractor of any responsibility, it simply accepts that the programme is realistic and that it can be used to assess future changes. If the programme is not accepted by the project manager, reasons for not accepting it must be given.
Reasons might include:
- It is not practical.
- It does not show required information.
- It does not properly represent the actual programme for activities.
- It does not show the full works.
Failure to accept or reject a programme may constitute a compensation event.
NEC4 introduces the new concept of ‘treated acceptance’, by which the project manager has a specified period of time to notify the contractor whether the programme has been accepted or not. If they fail to notify the contractor within this period, the programme is deemed to be accepted.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Baseline programme.
- Compensation event.
- Contract conditions.
- Contract data.
- Contractor's master programme.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early warning notice.
- Key dates.
- NEC contract change management systems.
- NEC early contractor involvement.
- NEC3.
- Programme.
- Programme for building design and construction.
- Programme narrative.
- Progress in construction.
- Short period programme.
- Tender works programme.
- Time Risk Allowance TRA.
- Works information.
- Z clauses.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.